Sequence and schedule

Below is an overview of the construction work scheduled to take place on the eighth and ninth floors of the Linnaeusborg.

> Also check the latest news.

Nuisance

Nuisance: what, where and when?

Construction work in

Period / date

Anticipated disruption

5172, 9th floor:
Move heating room to 0923

Completed end of May 2021 -

5172, 9th floor:
Upgrade Technical area North

May - September 2021

-

5172, 9th floor:
- cordoning off the area around 0923 and Technical Area North

Until mid-2021

-

Crane next to building

28 June 2021
12 July 2021

-

Minimization of disruption & Contact
It will not be possible to avoid disruption altogether but we will do all we can to keep it to a minimum.

The following steps will be taken to minimize disruption:

  • The most disruptive work will be carried out during the quietest periods (holidays or off-peak hours)
  • Whenever possible, internal transport will take place before 9 a.m.
  • Wherever possible, use will be made of fixed transport routes in the building (including use of the same lift)
  • henever possible, construction areas will be cordoned off to separate staff members from construction workers (also to facilitate compliance with coronavirus restrictions)
  • Use of radios will not be permitted
  • Regular updates will be issued about anticipated disruption via the website, the occupational health and environment contact person (AMV coordinator) and/or your secretariat
  • A round-the-clock contact service point will be available via reception (see below)

Contact

If you have a question or something you wish to report, please send an email to receptie.lb@rug.nl.

Schedule

Below is a broad overview of the renovation work that has already been completed on the eighth and ninth floors of the Linnaeusborg building and the work still pending.

Phase 1 (completed)

Phase 1

Over the last few months, the building team has been hard at work creating extra chemical lab facilities for the ARC Chemical Building Blocks Consortium (ARC CBBC) and the Stratingh Institute. On the ninth floor of building 5172, the first phase has now been completed. There are now two new labs, equipped with eighteen fume cupboards and eight under-bench cabinets for fixed workstations. The ventilation system has also undergone a major upgrade, providing for a potential 40% increase in the building’s air conditioning capacity.

Phase 2 (July 2020 - mid 2021)

Phase 2

The second and last project phase will include renovation work on the eighth floor, where existing practical laboratories will be converted into biochemical laboratories for the Chemical Biology 1 (GBB) group and the Stratingh Institute. This will create space on the ninth floor for the creation of the last three chemical laboratories for ARC CBBC. So, in this phase, a total of five new labs will be created with 33 fume cupboards and 18 under-bench cabinets on the eighth and ninth floors, for use by the Stratingh Institute and ARC CBBC.

Expansion of air filter system capacity
The capacity of the ventilation ducts will be further expanded and extra air handling units will be added to the ventilation system on the north side. In order to make the necessary changes to the ventilation system safely, the building will probably have to be closed for a short period towards the end of 2020. Further information will become available in due course.

Planning